Remodel scope and line-item bid request · Rev H · 4 September 2026

4000 Chamisa Dr: Whole-House Remodel, Phase 1

This document sets out the Phase 1 scope of work for the interior remodel of 4000 Chamisa Dr, Austin, Texas 78730, a two-level residence built in 1993: the work to be performed, the materials and finishes, the demolition drawings, the items still open, and the line items to be priced. Phase 1 comprises all work except the kitchen build-out and is to be complete by November 30, 2026. The kitchen build-out is Phase 2 and will be quoted separately. Bids may be submitted in the bidder's standard format, subject to the bid requirements below.

Revision H, 4 September 2026. Changes since the previous revision are marked in place: an amber note sits above each changed passage (0 in this revision); notes from earlier revisions are gray. Hide change notes
Revision history
  • Rev A · 3 Sep 2026 · First draft.
  • Rev B · 3 Sep 2026 · Made standalone. Phase 1 / Phase 2 split with the kitchen demolished and left. Transoms dropped. Floor method decided: underlayment out, glue-down to slab. Drywall in two groups with a Level 4 option; bathrooms out of wall work.
  • Rev C · 3 Sep 2026 · 6" cans replaced one-for-one, few additions (Item 2). Supply-piping check before wall work (Item 5). Fireplace reference photo added (Item 6).
  • Rev D · 3 Sep 2026 · Settled points folded into short summaries; only open questions remain as question-and-answer. Fireplace reduced to demo plus an $8,000 allowance with the reference photo; the earlier written design description is withdrawn. Assumed details removed (nosing overhang, skirt boards, carpet pad type, plate style, kitchen refrigerator circuit). Paint VOC requirement moved to Materials.
  • Rev E · 3 Sep 2026 · Existing conditions section removed. Supply-piping check removed: the piping was verified on 3 Sep and is not polybutylene, so lines 5.13 and 5.14 are gone. Change notes and this history now appear only when ?change is added to the address.
  • Rev F · 3 Sep 2026 · Bid instructions cut to one requirement: line items, in any format; the spreadsheet is gone. Window trim added to the trim scope (new line 4.7; the rest of Item 4 renumbered by one). Wall finish simplified to Level 3 or Level 4, priced for the downstairs and entry or for the whole house (Item 5).
  • Rev G · 3 Sep 2026 · Bid instructions expanded to five specific requests. Kitchen floor moved into Phase 1 with the rest of the first floor (Item 1); the Phase 2 appendix loses its flooring line and is renumbered. Walls bullet in The project reworded.
  • Rev H · 4 Sep 2026 · Video walkthrough added at the top: one strip of phone clips with a room filter. Owners' first counts folded in: 31 cans in seven rooms (Item 2, per room), 14 doors and openings (Item 4, per room), front office gets at least four new cans, and a count line in the kitchen, living room, office and primary bedroom items; later the same day the door count was completed at 14 with the entry closet, and the bowed-stud correction (former question 5.1 and line 5.5) was removed with the remaining Item 5 lines renumbered. Quantities stated for recessed lights (31 replaced, 4 new) and devices, with unit add/deduct prices for changes instead of unit prices without quantities; a bid form (Excel and CSV) generated from this page is linked under Bid requirements. Reference images for the door, applied moulding, casing, baseboard, the two hardware options and the stair rail added to Items 4 and 9. Item 12 restated as adding a tub where none exists (the demo line is gone; two lines remain). Bath One is called the downstairs bathroom throughout. The assumed multiple paint colors and contrast walls are removed (materials row PT-01, former line 5.9 and its decision row): wall color is settled as White Dove throughout. Transom glass added as an open item: frame stays, glass replaced, selection TBD (question 4.3, line 4.14). Window trim decided: drywall returns on all four sides, no casing, stool or apron; the window-casing question and the drywall alternate are removed, and the Item 4 questions and lines are renumbered. Item 13, Windows and exterior doors: full-frame replacement of every window in Phase 1 (16 first floor, 16 second floor from the drawings), black frames, set for the later stucco; the windows are in Phase 1 only if they can be on site by the contractor's required date, and the November 30 completion does not move for them (otherwise deferred to the exterior project, with line 4.15, keep and paint the existing casings, as the fallback); the contractor states whether the wall work waits for the windows because of the drywall returns (question 13.2); installation and the $2,500 placeholder allowance ($2,000 to $3,000 on selection) priced per floor so the first floor stands on its own (lines 13.1, 13.2, 13.4, 13.5); arched openings converted to rectangular at the spring line (line 13.3); the owners' questions and notes for the designer, including the cost of the second-floor windows, in a collapsible; front entry system and living room slider priced as alternates (question 13.3, lines 13.6 to 13.8), and the transom reglazing (4.14) becomes an alternate that applies only if the entry door is kept. Header reduced to one paragraph and the tag legend removed; wording revised throughout to a formal specification tone with no change in requirements; front office video to follow.
Walkthrough · 4 September 2026

The house on video

Video of each room in its current condition, recorded 4 September 2026, showing ceilings, recessed lighting, trim, doors and flooring. Select a room to filter the clips; each clip opens in a larger player, muted by default, with a full-screen control below the picture. The front office is not yet included and will be added shortly.

Kitchen 10:04
Kitchen 20:08
Kitchen 30:06
Kitchen 40:14
Kitchen 50:07
Living room 10:13
Living room 20:07
Living room 30:07
Living room 40:06
Living room 50:05
Living room 60:03
Dining room0:14
Entry 10:18
Entry 20:04
Stairs0:16
Upstairs hall0:30
Primary bedroom0:35
Primary bathroom0:23
Upstairs bedroom 10:19
Upstairs bedroom 20:29
Bid instructions

Bid requirements

Bids may be submitted in the bidder's standard format and shall meet the following requirements.

  • Itemize the work as line items, organized by room, by trade or by the bidder's usual structure, using the reference numbers in this document where they apply. Lump-sum pricing for the whole house without a line-item breakdown will not be accepted.
  • Where this document offers alternates (for example, keep or remove the crown molding), price each alternate as its own line item. Price the quantities stated in this document, and give a unit add/deduct price for each line whose quantity may change (recessed lights, devices).
  • State the quantities on which each price is based: square feet of flooring and wall surface, linear feet of baseboard, and counts of doors, windows, recessed lights and devices.
  • Identify allowances as allowances. Show owner-supplied items at zero material cost with installation priced.
  • State the fee or markup and the costs to which it applies, the proposed start date, and the expected duration of the work.

A bid form listing every line item in this document is provided as an Excel workbook, bid-form.xlsx, and as CSV. Completing the form is preferred. A bid in the bidder's own format is accepted if it carries the reference numbers.

Schedule

Phase 1 complete by November 30, 2026

Phase 1, comprising all work in this document, is to be complete by November 30, 2026. The earliest available start is preferred. State the proposed start date, the duration, and the intended sequence of trades (for example, wall finishing before flooring, flooring before base and doors). The replacement windows (Item 13) are owner-procured. State the date by which they must be on site to hold the completion date, and whether the wall work waits for them (questions 13.1 and 13.2). If they cannot be on site by that date, the windows are deferred to the exterior project and the completion date stands.

The kitchen is demolished in Phase 1 and remains demolished for the duration of Phase 1. The kitchen build-out cannot be completed within the Phase 1 schedule. The kitchen is therefore demolished, capped and made safe, and the remainder of the house is completed with the kitchen removed. The build-out is Phase 2, quoted separately on its own schedule (see the appendix).

Scope

The project

A full interior finish renovation of both floors of a 1993 two-level house, together with the specific items listed below. In summary:

Materials

Materials and finish schedule

State trade pricing and freight. Confirm every selection with the owners before ordering. Items marked owner-provided are installed by the contractor. All paint is zero-VOC (water-based) or low-VOC (oil-based); name the product lines priced, and apply the same preference to primers and, where practical, the flooring adhesive.

KeyItemSpecificationStatus
FL-01Wood flooring, first floor and stair treadsOpus Signature Series engineered hardwood, 5/8" × 9½" plank. Glue-down direct to slab with premium urethane wide-plank adhesive. Available through Landers Premier Flooring (Austin); may be sourced elsewhere at equal or better price.Color to confirm
FL-02Carpet, second floorKarastan, Tower View, color Atrium. Pad: specify the product priced.Product to confirm
ST-01Stair handrail and newel postsSolid wood of the flooring species, stained and finished to match FL-01. Fabricator per contractor.TBD design
ST-02Stair balustersMetal, black finish.TBD profile
ST-03Stair risersPaint grade, Benjamin Moore White Dove OC-17.
TR-01Baseboards throughout6" tall, paint grade, routed top edge.
TR-02Casings at doors and cased openings4" × 1" flat stock, paint grade. Same profile everywhere. Windows: drywall returns on all four sides, no casing, stool or apron.
TR-03Crown moldingKeep and repair, or remove; see Item 4.1. If kept, entry crown replaced to match.TBD on cost
DR-01Interior doorsFlat panel, paint grade, with ½" applied moulding set 6" in from the door edge, mitered corners. 14, per Item 4.
DR-02Door hardwareBrass lever; two styles under consideration (rectangular or square rose). Owner-provided.TBD style
PT-01WallsBenjamin Moore White Dove OC-17, washable matte/flat, all walls; satin in bathrooms, closets and laundry.
PT-02CeilingsBenjamin Moore White Dove OC-17, flat.
PT-03Doors, trim, baseboards, casingsSherwin-Williams Shoji White SW 7042, semi-gloss.
EL-01Recessed lightingLED, 2700K, 6" round, white trim, replacing the existing 6" cans in place. Four new locations in the front office (Phase 1), possibly more; the kitchen is Phase 2.TBD added locations
EL-02Switches, dimmers, receptacles, platesPaddle style, Lutron or equal, assumed for bidding.TBD selection
EL-03Decorative fixtures, Phase 1Entry pendant, dining pendant, living room ceiling fixture (replaces the fan). Owner-provided.TBD selection
FP-01Fireplace surroundFloor to ceiling, per the reference photo in Item 6. $8,000 allowance. Details to follow.TBD details
PB-01Free-standing tub and fillerOwner-provided, $5,000 allowance.TBD
WN-01WindowsFull-frame replacement units with nailing fins, black frames, set for the later stucco exterior; arched openings converted to rectangular at the spring line. Product to be selected and procured by the owners; carried at $2,500 per window ($2,000 to $3,000) until then.TBD product
DR-03Front entry system: door, sidelights and transomOwner-selected. Whether it is replaced is not decided (Item 13).TBD
DR-04Living room sliding glass doorOwner-selected. Whether it is replaced, and its size, are not decided (Item 13).TBD
Drawings

Demo plans

Four sheets: first and second floor demo plans, each with a dimensioned version and a noted version. Click a sheet to view it at full size, or download the PDF. Notes on the sheets marked N/A are not part of this project. The wall finish level is per Item 5, not the note on the sheets.

Drawing 1: first floor demo plan with dimensions
Drawing 1 · First floor demo plan with dimensions. Overall first-floor envelope 57'-3" × 32'-10". Ceilings 10'-0" except the entry at 20'-7". Dashed lines indicate demo scope; the dashed bay at the breakfast room and the dashed pantry wall are N/A (see Drawing 2).
Drawing 2: first floor demo plan with notes
N/A
N/A
N/A
N/A
Drawing 2 · First floor demo plan with notes.
  • N/A: the bay window note and the pantry note. The bay and the pantry stay as built.
  • Downstairs bathroom (Bath One on the sheet): the existing flooring comes out (the sheet says "to remain"); see Item 8. The vanity light box moves to center on the vanity.
  • Front room: "demo existing millwork" includes the gun case.
  • Entry: the abandoned security panel and doorbell chime come out along with the sconces.
  • The existing decorative transom stays; its glass is replaced (Item 4, question 4.3).
  • Sconce removal, fireplace demo, ceiling fan replacement, pendant replacements, kitchen demo, and stair demo apply as drawn.
Drawing 3: second floor demo plan with dimensions
Drawing 3 · Second floor demo plan with dimensions. Overall second-floor envelope 44'-7" × 30'-8". Ceilings 9'-0" typical; primary bath vault 17'-8". Carpet comes out everywhere shown "flooring to be demo'd"; Bath Two and Primary Bath flooring stay.
Drawing 4: second floor demo plan with notes
Drawing 4 · Second floor demo plan with notes.
  • Both primary closets: demo the built-in chests; patch and finish (Item 11).
  • Bathrooms: no wall texture work, regardless of the sheet note. The primary bathroom gets a new tub in Item 12.
  • Sconce removal in the hallway and the stair demo apply as drawn.
Item A

A. General conditions

Carry these as separate lines. Dumpsters at actual cost, per pull.

RefLine itemUnitTypeNotes
A.1Site protection: floors, stairs and surfaces to remain, dust partitions, HVAC register protection, both levelsLSBase
A.2Temporary facilities: portable toilet, temporary power and water as neededLSBase
A.3Debris haul-off / dumpstersper pullUnit priceState container size and the expected number of pulls. Billed at actual cost.
A.4Weekly clean and final cleanLSBase
A.5Supervision, project management, and overhead/feeLS or %BaseState how the fee or markup is applied (to which lines, and whether to allowances and owner-supplied items).
Item 1

1. Hardwood and carpet

Opus Signature Series engineered hardwood, 5/8" × 9½" plank, on the whole first floor except the laundry, kitchen included, and on the stair treads. The existing hardwood and its plywood underlayment come out down to the slab; the slab is cleaned, patched and moisture-tested; the new floor is glued direct with a premium urethane wide-plank adhesive, which is how the flooring store recommends installing this product. The finished floor ends up lower by the plywood thickness, so the exterior door thresholds, the laundry transition and the bottom stair riser are priced separately (lines 1.6 and 9.3).

Upstairs: Karastan Tower View carpet, color Atrium, in the bedrooms, closets and hallway. Colors and products are confirmed against samples before ordering. Flooring may be contracted directly with the flooring supplier; price it as a separate group so that it can be removed without affecting the remainder of the bid.

Line items requested

RefLine itemUnitTypeNotes
1.1Demo existing hardwood and plywood underlayment down to the slab, first floor, including haulSFBaseAll first-floor wood rooms per Drawing 2 plus the downstairs bathroom. Kitchen included (Item 7). Laundry excluded.
1.2Demo existing carpet and pad, second floor, including haulSFBaseRooms per Drawing 4.
1.3Slab prep: scrape and clean, patch and level (cement patch), moisture testSFBaseState the patch product and the quantity assumed; additional patching may be required once the slab is exposed.
1.4Engineered hardwood material: Opus Signature Series, 5/8" × 9½" plankSFBaseState waste factor, trade price and freight separately. Color to be confirmed before order.
1.5Hardwood install, glue-down direct to slab, including premium urethane wide-plank adhesiveSFBaseWhole first floor including the kitchen; not the laundry.
1.6Height change at the lower finished floor: exterior door thresholds, transition to laundry tile, and any other transitionsEA / LSBaseList locations. Bottom stair riser is handled in 9.3.
1.7Carpet material: Karastan, Tower View, color AtriumSYBaseState waste factor and freight. Product to be confirmed before order.
1.8Carpet pad and install, second floor bedrooms, closets and hallwaySFBaseSpecify the pad priced. Tack strip, seams, trim.
Item 2

2. Lighting

Existing 6" recessed cans are replaced one-for-one with new 6" LED cans (2700K, white trim), in place. The owners' count to date is 31: kitchen 4, living room 8, front office 3, dining room 4, primary bedroom 4, upstairs bedroom 1 four, upstairs bedroom 2 four. The remaining rooms have not been counted; state the total counted at the walkthrough. Decorative fixtures are owner-provided and installed by the contractor; in Phase 1 these are the entry pendant (20'-7" ceiling, lift), the dining pendant, and the living room ceiling fixture that replaces the fan. The sconces in the entry and the upstairs hall come out.

2.1

How many cans to add in the front office (Phase 1) and the kitchen (Phase 2)?

TBDFront office: at least four new cans (three existing). Kitchen: Phase 2. Line 2.2 carries four; state a unit add for additional locations.

Line items requested

RefLine itemUnitTypeNotes
2.1Replace existing 6" recessed can, one-for-one, with new 6" LED can, 2700K, white trim (retrofit into existing housing or new housing as needed)EABaseQuantity 31, the owners' count (per room above); verify. State a unit add/deduct. State whether the existing housings are reused or replaced.
2.2New 6" LED recessed can at a new location, 2700K, white trim, wired to existing or new switchingEABaseQuantity 4, front office (the minimum wanted). State a unit add for additional locations. The kitchen is Phase 2.
2.3Install owner-provided decorative fixtures: dining pendant, living room ceiling fixture replacing the fanEABaseConnect to existing switching.
2.4Install owner-provided entry pendant at 20'-7" ceiling, including liftEABase
2.5Remove sconces, abandon j-box, patch: Entry (2), Second Floor Hallway (2)EABase
2.6Electrical general: new homeruns, circuits and panel work required by lighting and device changesLSBaseKeep separate from the per-light prices.
Item 3

3. Light switches, outlets and covers

New switches, dimmers, receptacles and plates in all Phase 1 rooms. Dimmers that control no load are removed, the box removed and the wall patched; confirm with the owners before removing any device found to control a load.

3.1

Which switches and plates?

TBDNot selected. For bidding assume paddle-style devices and plates, Lutron or equal. Split material and labor so the selection can change without re-bidding.

Line items requested

RefLine itemUnitTypeNotes
3.1New switches, dimmers, receptacles and plates throughout the Phase 1 roomsEABaseCount the devices at the walkthrough and state the quantity priced; state a unit add/deduct. Assume paddle-style devices and plates, Lutron or equal. Separate material and labor so that the selection can change.
3.2Remove dead or unconnected dimmers/switches, remove box, patchEABaseConfirm with the owners before removing any device that controls a load.
Item 4

4. Trim and crown molding

All baseboards, door casings, window casings, trim and interior doors come out and are replaced: 6" paint-grade baseboard with a routed top edge; 4" × 1" flat-stock casing at every door and every cased opening; window openings finished in drywall on all four sides, with no casing, stool or apron; flat-panel paint-grade doors with ½" applied moulding set 6" in from the edge, mitered corners, 14 in total; owner-provided hardware installed. The existing decorative transom stays; its glass is replaced with new glass, not yet selected (question 4.3). Doors and openings, 14: pantry door 1, doors leading to the kitchen 3, entry closet 1, front office french-door opening 1, primary bedroom 4, upstairs bedroom 1 two, upstairs bedroom 2 one door and one sliding closet door.

Reference image: flat-panel painted door with applied moulding
Door: flat panel, paint grade, ½" applied moulding set 6" from the edge, mitered corners.
Reference image: half-inch applied moulding strip
Applied moulding, ½", paint grade.
Reference image: flat stock door casing
Casing: 4" × 1" flat stock, paint grade, at doors, windows and cased openings.
Reference image: 6-inch baseboard with routed top edge
Baseboard: 6", paint grade, routed top edge.
Reference image: brass lever on a rectangular rose
Door hardware, owner-provided: brass lever, option A, rectangular rose.
Reference image: brass lever on a square rose
Door hardware, owner-provided: brass lever, option B, square rose.

Reference images show the intended style and are not for matching.

4.1

Keep or remove the crown molding?

AlternateTBDPrice both: A, keep, repair, caulk and paint it everywhere it exists (line 4.8); B, remove it all, patch and finish (line 4.9). If it is kept, the entry crown is replaced with a matching profile at the 20'-7" ceiling (line 4.10). State whether the crown must be removed for the Level 3 or Level 4 work in Item 5.

4.2

Front office crown: replace it, or paint the dark wood in place?

AlternateTBDPrice both (lines 4.11 and 4.12). The selection will be made on cost and on the contractor's assessment of how well the stained wood will take paint.

4.3

Transom glass: what replaces the existing glass?

TBDThe transom frame stays and the existing glass is replaced. The new glass is not yet selected. Price the removal and reglazing labor now (line 4.14); the glass is priced when selected. If the front entry system is replaced (Item 13), the transom goes with it and line 4.14 does not apply.

Line items requested

RefLine itemUnitTypeNotes
4.1Demo all baseboards, door casings, trim and interior doors, both levels (kitchen trim goes with the kitchen demo)LSBase
4.2Baseboard: 6" paint grade with routed top edge, both levelsLFBaseState the linear footage. Not in the kitchen in Phase 1.
4.3Interior doors: flat panel paint grade slab, jamb, ½" applied moulding 6" inset with mitered corners, hang and adjustEABase14 (per room above).
4.4Door casing: 4" × 1" flat stock, paint grade, both sidesper doorBase
4.5Door hardware install (owner-provided)EABaseBore, set, adjust.
4.6Casing at cased openings, new profile to match door casingsEA openingBaseList openings.
4.7Window openings: remove existing casings, stools and aprons; drywall returns on all four sides at every new window (Item 13) in the Phase 1 rooms, built after the windows are installedEA windowBaseState the window count.
4.8ALTERNATE A: keep existing crown: protect, repair, caulk and paintLSAlternateState whether the drywall approach (Item 5) requires its removal.
4.9ALTERNATE B: remove all crown, patch and finish walls and ceilingsLSAlternate
4.10Entry crown: replace with a profile matching the rest of the house, including lift (if crown is kept)LFBase
4.11Front office crown: replace to match the rest of the houseLFAlternatePrice both 4.11 and 4.12; selection on cost.
4.12Front office crown: prime and paint the existing dark wood crown in placeLSAlternate
4.13Paint all trim, doors, casings and base: SW Shoji White 7042, semi-gloss, zero/low VOCLSBase
4.14ALTERNATE, if the front entry door is kept: transom, remove the existing glass and install new glass; glass type TBDLSAlternateApplies only if the front entry system is not replaced (Item 13). Price the labor now; the glass is priced when selected (question 4.3).
4.15ALTERNATE, if the windows are deferred (Item 13): keep the existing window casings, stools and aprons; prep and paint; drywall returns not builtEA windowAlternatePriced in case the windows cannot be delivered in time; see question 13.1.
Item 5

5. Walls, ceilings and paint

Four prices are requested; one will be selected. Level 3 (tape and float, new light texture) or Level 4 (tape and float with a full third coat, no texture, ready for flat paint), each priced two ways. Downstairs and entry: the first-floor rooms and the two-story entry, not the pantry, the mudroom (the laundry on the drawings) or the downstairs bathroom. Whole house: the same plus the second floor, still not the pantry, the mudroom or any bathroom. The kitchen walls and ceiling are Phase 2 either way. Paint is throughout under either option; the bathrooms are a separate paint line so that they can be removed from the scope.

Line items requested

RefLine itemUnitTypeNotes
5.1Level 3 refinish, downstairs and entry: tape and float, new light texture, walls and ceilingsSFOptionState the square footage and the texture proposed. Include the 20'-7" entry.
5.2Level 4 refinish, downstairs and entry: tape and float with a full third coat, no textureSFOptionState the SF.
5.3Level 3 refinish, whole houseSFOptionDownstairs and entry plus the second floor; no pantry, mudroom or bathrooms.
5.4Level 4 refinish, whole houseSFOption
5.5Patch, float and finish at all demo locations (millwork, built-in chests, sconces, removed devices, security panel, vanity light relocation)LSBaseOr state that it is included above.
5.6Paint walls throughout: BM White Dove OC-17, washable matte; satin in closets and laundrySFBaseAll Phase 1 rooms except bathrooms. State the product line. Primer included.
5.7Paint ceilings throughout: BM White Dove OC-17, flatSFBaseInclude the 20'-7" entry.
5.8Bathrooms: paint walls and ceilings, satin, no drywall workper bathroomBaseQuantity 3: the downstairs bathroom, Bath Two and the primary bathroom (17'-8" vault). State a unit deduct per bathroom; any of these rooms may be removed from the scope.
Item 6

6. Living room fireplace

Demo the existing hearth, mantel and brick surround (line 6.1). New floor-to-ceiling surround per the reference photo below: $8,000 allowance (line 6.2). Further detail to follow. The ceiling fixture that replaces the fan is owner-provided; install is in line 2.3.

Counted so far in the living room: 8 existing cans; no doors.

Reference photo for the fireplace surround
Reference for the fireplace surround

Line items requested

RefLine itemUnitTypeNotes
6.1Demo hearth, mantel and brick surroundLSBase
6.2New floor-to-ceiling surround per the reference photoAllowanceAllowance$8,000 allowance. Details to follow.
Item 7

7. Kitchen

Phase 1 is a full demo, then cap and make safe, then leave it: remove cabinetry, countertops, backsplash, the island, plumbing fixtures, decorative lighting and trim; disconnect and remove the appliances (the owners will identify which are kept); cap the plumbing and gas, cap the island vent, and make the electrical safe. The new flooring runs through the kitchen in Phase 1; the kitchen walls and ceiling are finished in Phase 2. Phase 2The build-out is a separate quote on its own schedule; the appendix summarizes it for reference. Do not include it in the Phase 1 price.

Counted so far: 4 existing cans; 1 pantry door, plus 3 doors leading to the kitchen.

7.1

The kitchen–dining opening is shorter than the dining–entry opening. Raise it to match?

AlternateContractorTBDPrice it as a Phase 1 alternate (line 7.3), since the dining-room side is getting wall work now: raise the head of the opening to match the dining–entry opening, including header, dining-side drywall, casing and finish. State whether the wall is load-bearing and, if so, the proposed structural approach.

Line items requested

RefLine itemUnitTypeNotes
7.1Full kitchen demo: cabinetry, countertops, backsplash, island, plumbing fixtures, decorative lighting, trim; disconnect and remove appliances; haulLSBaseThe owners will identify which appliances are kept and set aside.
7.2Cap and make safe: plumbing, gas, island vent; electrical made safeLSBase
7.3ALTERNATE: raise the head of the kitchen–dining opening to match the dining–entry opening height: header, dining-side drywall, casing, finishLSAlternateState whether the wall is load-bearing and the proposed approach if it is.
Item 8

8. Downstairs bathroom

The downstairs bathroom (Bath One on the drawings) receives the new hardwood in Phase 1, by the same glue-down method: existing floor out to the slab, toilet pulled and reset, transition at the door (line 8.1). The vanity light box moves to center on the vanity (line 8.2). No other wall work in this room; paint is line 5.8.

RefLine itemUnitTypeNotes
8.1Downstairs bathroom flooring: existing floor out to the slab, toilet pulled and reset, slab prep, glue-down hardwood, transition at doorLSBase
8.2Relocate the vanity light j-box to center on the vanity; patchEABase
Item 9

9. Entry and staircase

New Opus treads with matching stairnose (16, verify) over painted risers, Benjamin Moore White Dove OC-17 (17, verify). New handrail and newel posts in solid wood of the flooring species, stained to match the floor; black metal balusters. Because the first floor drops by the plywood thickness (Item 1), the bottom riser gets taller: include the correction in line 9.3 and state how even riser heights will be maintained. In the entry, the abandoned security panel and keypads, the doorbell chime, and any other abandoned wall devices found at the walkthrough are removed, wiring abandoned safely and walls patched (line 9.6); whether a replacement chime is wanted is undecided.

Counted in the entry: 1 closet door.

Reference image: wood handrail and newel posts with thin black metal balusters
Handrail, newel posts and metal balusters: reference image for the intended style. Design details open per 9.1.
9.1

Stair design: tread construction, how far the treads extend, post design, baluster profile, who fabricates the rail?

TBDContractorAll open. Propose the tread construction (solid tread or plank-wrapped with stairnose) and price both if they differ; state the recommended nosing overhang. Name the proposed fabricator for the rail and posts, or advise whether the owners should purchase them directly, and provide stain samples on the actual species. Opus stairnose pieces exist and have been priced for this staircase before; confirm availability and lead time. An engineered plank cannot be milled into a rail or post, which is why the rail and newels are solid wood matched to the floor.

Line items requested

RefLine itemUnitTypeNotes
9.1Demo stair treads, railing, balusters and newel posts; temporary safety rail during constructionLSBase
9.2Stair tread material: Opus tread or plank with matching stairnoseEABase16 treads assumed; field verify. State the proposed tread construction.
9.3Stair tread fabrication and install, including skirt and nosing detail and the bottom-riser adjustment for the lower first floorEABaseState how even riser heights will be maintained.
9.4Risers: prep and paint BM White Dove OC-17EABase17 assumed; field verify.
9.5Handrail and newel posts: solid wood of the flooring species, stained and finished to match the floor; black metal balustersLF rail + EA newelBaseName the fabricator. Provide stain samples. Post design TBD.
9.6Remove abandoned security panel(s) and keypad, doorbell chime, and other abandoned wall devices; abandon wiring safely; patchLSBaseReplacement chime TBD; may be priced as an optional add.
Item 10

10. Front office

All built-in cabinetry, including the gun case, comes out and is hauled; the wall and floor are repaired at the demo (lines 10.1 and 10.2). Crown: see Item 4.2.

Counted so far: 3 existing cans, at least 4 to add (Item 2); 1 french-door opening.

10.1

What happens to the french doors?

AlternateTBDUndecided. Price three alternates: A, keep them, prep and paint (line 10.3); B, replace them with new doors to the door spec and install owner-provided hardware (line 10.4); C, remove the doors and jamb and case the opening (line 10.5).

Line items requested

RefLine itemUnitTypeNotes
10.1Demo all built-in cabinetry including the gun case; haulLSBase
10.2Wall and floor repair at millwork demoLSBase
10.3French doors ALTERNATE A: keep, prep and paintLSAlternate
10.4French doors ALTERNATE B: replace with new doors to the door spec (flat panel, applied moulding), hang, install owner-provided hardwareLSAlternate
10.5French doors ALTERNATE C: remove doors and jamb, case the openingLSAlternate
Item 11

11. Primary bedroom closets

The built-in chests in both primary closets come out and are hauled; walls and floor are patched and finished; nothing goes back in their place. The closets then get carpet, base and paint with the rest of the second floor.

Counted so far in the primary bedroom: 4 existing cans; 4 doors.

RefLine itemUnitTypeNotes
11.1Demo built-in chests in both primary closets; haulLSBaseNothing goes back in their place.
11.2Patch and finish walls and floor at demoLSBase
Item 12

12. Primary bathroom, new tub

There is no tub in the primary bathroom today; the space for one exists. Install a new free-standing tub and tub filler (owner-provided, $5,000 allowance) in that space, with new supply and drain connections. Existing flooring and walls otherwise stay; patch and paint only where the tub work disturbs them.

RefLine itemUnitTypeNotes
12.1Free-standing tub and filler: new supply and drain to the tub location, rough-in, set and finish (owner-provided tub and filler, $5,000 allowance)LSBaseNo tub exists today; the space for one does.
12.2Patch and paint where the tub work disturbs the floor and wallsLSBase
Item 13

13. Windows and exterior doors

Schedule condition. The windows are in Phase 1 only if they can be on site by the date the contractor requires. The November 30, 2026 completion date does not move for the windows. The contractor states the required-on-site date, and whether the wall work waits for the windows (questions 13.1 and 13.2). If the windows cannot be on site by that date, they are deferred to the later exterior project, Phase 1 proceeds without them, and the existing window casings are kept and painted (line 4.15).

Scope. Every window is replaced with a full-frame unit: black frames, nailing fins to the sheathing, flashing integrated with the existing weather barrier. The exterior will be redone in stucco in a later project, so no exterior brickmould is installed, and temporary exterior trim at each opening is made weathertight until the stucco work. The interior of each opening is left ready for the drywall return (line 4.7).

Arched openings. The four arched living room openings are converted to rectangular at the existing head height, the spring line of the arch: infill framing and sheathing, flashing, and the exterior patched weathertight until the stucco work (line 13.3).

Pricing by floor. Installation and the unit allowance are priced separately for the first floor (16 windows) and the second floor (16 windows). The first floor is priced so that it stands on its own. A lower-cost product is under consideration for the second floor, and the second-floor selection may differ from the first. The units are not yet selected; the owners procure them through their designer. Each is carried at a $2,500 allowance, to be set between $2,000 and $3,000 on selection, or owner-provided if the owners purchase directly.

Exterior doors. The front entry system (door, sidelights and transom as one unit) and the living room sliding glass door may also be replaced. Neither the decision nor the products are settled. Installation is priced as alternates; the units are owner-selected (question 13.3).

Count from the drawings, by glazed unit, with mulled assemblies counted per unit; verify at the walkthrough. First floor, 16: living room 3, breakfast bay 4, kitchen 1, laundry 1, front room 4 including its bay, dining room 2, downstairs bathroom 1. Second floor, 16: primary bedroom 5 including a three-unit assembly, primary bathroom bay 7, bedroom two 2, bedroom three 2. The two sidelights at the front door belong to the entry system, not the window count.

Questions and notes for the designer

Second-floor windows: how can the second-floor windows be made less expensive? The first floor is priced on its own (lines 13.1 and 13.4) so that the second floor can be decided separately.

Anticipated windows. The selection is open, and the schedule decides whether the windows are in Phase 1. The anticipated product:

  • Frame: black inside and out, narrow profile. Fiberglass, aluminum-clad wood or thermally broken aluminum; not vinyl, which fades and warps in black in this sun.
  • Type: full-frame replacement units with nailing fins, set to the sheathing, so the later stucco can build to them. No exterior brickmould.
  • Shape: rectangular throughout. The four arched living room openings are squared at the spring line (line 13.3). No radius-top or fan-lite units; they are custom and slow, and the designer's living room rendering, which keeps the arches, should be reconciled with this.
  • Grid: the thin black steel-window look. Simulated divided lites (SDL) bonded to both faces of the glass with a matching black spacer bar between the panes, bars about 5/8" to 7/8", black. Pattern tall and narrow: two lites wide, about four high on the tall openings. Not grilles between the glass and not snap-in grilles.
  • Operation: casement or fixed. No double-hung; the meeting rail cuts across the grid.
  • Lines that do this: Marvin (Elevate, Ultimate, Modern), Andersen E-Series, Pella Reserve, Kolbe, Sierra Pacific; steel-look aluminum from Western Window Systems or Fleetwood; true steel from Rehme or Portella, both Austin.
  • Budget: $2,000 to $3,000 per window carried in the bid. SDL adds roughly $300 to $400 per window on a fiberglass or clad line; true steel is a different price class.
  • Schedule: the windows must be on site by the date the contractor states (question 13.1). Standard rectangular sizes in black are the fastest path.
  • Doors to match: the front entry system (door, sidelights, transom) and the living room slider in the same black frame and grid language, if they are replaced.
13.1

By what date must the windows be on site?

ContractorState the date by which the windows must be on site to hold the November 30, 2026 completion. The completion date does not move for the windows. If they cannot be on site by the stated date, they are deferred to the exterior project, Phase 1 proceeds without them, and the window openings are treated per line 4.15.

13.2

Do the windows hold up the wall work?

ContractorThe drywall returns (line 4.7) are built after the windows are in. State whether the rest of the wall finishing (Item 5) can proceed before the windows are installed, with only the returns left for after them, or whether the windows must be in place before the wall finishing begins. State how each answer affects the required-on-site date in question 13.1.

13.3

Replace the front entry door and the living room sliding glass door?

AlternateTBDNot decided, and neither product is selected. Price the installation as alternates (lines 13.6 to 13.8); the units are owner-selected. The entry is one system: door, sidelights and transom. If it is replaced, the transom reglazing in line 4.14 does not apply. The sliding door may stay the same size or be widened; the widening is priced when the size is known.

Line items requested

RefLine itemUnitTypeNotes
13.1First-floor windows: remove existing unit; install owner-selected full-frame unit with nailing fin, flashing integrated with the existing weather barrier, temporary exterior trim made weathertight, interior ready for the drywall return; dispose of the old unitEA windowBaseQuantity 16 from the drawings; verify. Price oversized or specialty units separately.
13.2Second-floor windows: same scope as 13.1EA windowBaseQuantity 16 from the drawings; verify. Price oversized or specialty units separately. Priced separately from the first floor.
13.3Convert arched window opening to rectangular at the existing head height (spring line of the arch): infill framing and sheathing, flashing, exterior patch made weathertight until the stucco work, interior ready for the drywall returnEA openingBaseQuantity 4, the living room; verify and state any other arched openings.
13.4Window units, first floor: black frames, nailing fin, product to be selected by the ownersEA windowAllowancePlaceholder $2,500 per window, 16 windows; the owners set the amount between $2,000 and $3,000 on selection. Owner-provided if the owners purchase directly.
13.5Window units, second floor: black frames, nailing fin, product to be selected by the owners; a lower-cost product is under considerationEA windowAllowancePlaceholder $2,500 per window, 16 windows; the owners set the amount on selection. Owner-provided if the owners purchase directly.
13.6ALTERNATE: front entry system: remove the existing door, sidelights and transom; install the owner-selected unit, flash, temporary exterior trim, threshold to the new floorLSAlternateUnit owner-selected. If taken, line 4.14 does not apply.
13.7ALTERNATE: living room sliding glass door: remove the existing unit; install the owner-selected unit in the existing opening, flash, temporary exterior trim, threshold to the new floorLSAlternateUnit owner-selected.
13.8Widen the sliding-door opening for a larger unit: header, framing, exterior and interior patchLSContingentPriced when the size is selected.
13.9Exterior door units: front entry system and sliding glass door, owner-selectedEAOwner-suppliedNot priced; receiving and handling only.
Decisions

Open decisions log

Items still open, the party responsible for each decision, and how each is handled in the bid so that pricing can proceed.

RefDecisionOwnerNeeded to decideBid treatment
1Opus color; confirm carpet productOwnersSamplesPrice as listed; color does not change price
2.1Added can lights in the front office (Phase 1, at least four) and kitchen (Phase 2)OwnersFour priced; unit add for moreLine 2.2 at four; line 2.1 replaces 31 one-for-one
EL-03Decorative fixture selectionsOwnersSelectionsOwner-provided; install labor priced
3.1Switch, dimmer and plate selectionOwnersSelectionAssume paddle-style, Lutron or equal; material and labor split
4.1Keep or remove crownOwnersAlternates A and B; drywall option chosenAlternates 4.8 / 4.9; 4.10 if kept
4.2Front office crown: replace or paintOwnersTwo alternate pricesAlternates 4.11 / 4.12
4.3Transom glass selectionOwnersSelectionLabor on line 4.14; glass priced when selected
13.1Window product, black frames; delivery by the contractor's required-on-site dateOwners, with their designerSelection; delivery dateInstall per window (13.1, 13.2); units at $2,500 allowance per floor (13.4, 13.5); deferred with fallback 4.15 if the windows cannot be on site by the contractor's required date
13.3Front entry system and living room sliding door: replace or not; products; slider sizeOwnersDecision and selectionsAlternates 13.6 to 13.8; units owner-selected
5Level 3 or Level 4; downstairs and entry, or whole houseOwnersFour pricesLines 5.1–5.4
6Fireplace details beyond the reference photoOwnersMore to comeDemo line 6.1; $8,000 allowance line 6.2
7.1Raise kitchen–dining openingOwnersAlternate price; structural answerAlternate 7.3
9.1Stair design: tread construction, nosing, newel posts, baluster profile, fabricatorOwners with contractorProposal and samplesPrice both tread constructions
9Replacement doorbell chimeOwnersPreferenceOptional add
10.1French doors: keep, replace or removeOwnersThree alternate pricesAlternates 10.3–10.5
DR-02Door hardware styleOwnersPreferenceOwner-provided; install priced per door
Appendix

Kitchen build-out, Phase 2 Separate quote

Not part of the Phase 1 price. Listed for reference, to be quoted separately when the design is final. Working assumptions: new layout with a larger island; stain-grade flat-panel cabinetry, about 41 LF on the range and sink walls including uppers, 7 LF of floor-to-ceiling cabinetry at the fridge wall with an appliance garage, and 6 LF of island millwork; Level 5 quartzite countertops with a mitered edge; tile backsplash at a $20/SF allowance; under-cabinet LED tape; a decorative vent hood ducted to the exterior; the range moves off the island. Owner-provided: appliances ($36,000 allowance), plumbing fixtures ($6,000 allowance), cabinet hardware, and three pendants.

RefLine itemUnitTypeNotes
K.1Layout modification and new framing per final planLSBase
K.2New threshold, framing and concealed door to hallwayLSBase
K.3Cabinetry: range wall and sink wall including uppers, stain-grade flat panel doors and drawers (~41 LF)LFBaseState whether finishing is included; if not, see K.6.
K.4Cabinetry: fridge wall, floor to ceiling, with appliance garage (~7 LF), stain gradeLFBase
K.5Island millwork (~6 LF, larger island), stain gradeLFBase
K.6Cabinet finishing (if not in K.3–K.5)LFBase
K.7Decorative vent hood fabricationAllowanceAllowanceDesign, material and finish TBD.
K.8Countertop material: Level 5 quartziteper slabAllowanceState the slab count assumed.
K.9Countertop fabrication and install: template, mitered edge, cutouts, seams, setSFBase~130 SF; verify against final elevations.
K.10Backsplash tile materialSFAllowance$20/SF allowance.
K.11Backsplash install: prep, set, grout, sealSFBase
K.12Under-cabinet LED tape 2700K with concealed routed detail or trim, driver and dimmingLFBase~32 LF assumed.
K.13Kitchen electrical rough and finish: appliance circuits, island, disposal, hood, devices, 6" can lightsLSBase
K.14Kitchen plumbing rough and finish for the new layout; set owner-provided fixtures and disposalLSBaseFixtures owner-provided ($6,000 allowance): sink, faucet, hot/cold/sparkling faucet, disposal.
K.15Gas line relocation to the new range wall, if requiredLSContingent
K.16Range hood duct to exterior; chase framing and patchLSBaseState the route assumed.
K.17Makeup air system if the hood exceeds 400 CFMLSContingent
K.18Kitchen walls and ceiling: finish to the level chosen in Item 5; paintSFBase
K.19Appliance delivery, set and install (owner-provided package, $36,000 allowance)LSBase
K.20Cabinet hardware install (owner-provided, ~62 pieces)EABase
K.21Install owner-provided pendants: sink (1), island (2)EABase