What we want done, what it is made of, the drawings, the questions still open, and the line items we would like priced. Phase 1 is everything except the kitchen build-out and needs to be finished by the end of November 2026.
?change is added to the address.This is meant to be light. Walk the house with us, then give us a price broken into line items we can read. Use whatever format you normally use, as long as it does the following.
Every line item in this document is also in chamisa-bid-form.csv with blank quantity, unit price, extended and sub-quote columns, if a spreadsheet is easier.
Phase 1, everything in this document, complete by November 30, 2026. We would like to start as soon as you can. Tell us your realistic start date, duration, and how you would sequence it (walls before floors, floors before base and doors, and so on).
The kitchen is demolished in Phase 1 and stays demolished. The kitchen build-out will not finish in time, so the plan is to demo it, cap and make it safe, and do the rest of the house with the kitchen removed. The build-out is Phase 2, quoted separately (see the appendix) on its own schedule.
A 1993 two-story house getting a full cosmetic layer on both floors plus a handful of specific items. In short:
State your trade pricing and freight. Confirm every selection with us before ordering. Items marked owner-provided are installed by the contractor. All paint is zero-VOC (water-based) or low-VOC (oil-based); name the product lines you are pricing, and apply the same preference to primers and, where practical, the flooring adhesive.
| Key | Item | Specification | Status |
|---|---|---|---|
| FL-01 | Wood flooring, first floor and stair treads | Opus Signature Series engineered hardwood, 5/8" × 9½" plank. Glue-down direct to slab with premium urethane wide-plank adhesive. Available through Landers Premier Flooring (Austin); source elsewhere at equal or better price if you like. | Color to confirm |
| FL-02 | Carpet, second floor | Karastan, Tower View, color Atrium. Pad: specify what you price. | Product to confirm |
| ST-01 | Stair handrail and newel posts | Solid wood of the flooring species, stained and finished to match FL-01. Fabricator per contractor. | TBD design |
| ST-02 | Stair balusters | Metal, black finish. | TBD profile |
| ST-03 | Stair risers | Paint grade, Benjamin Moore White Dove OC-17. | |
| TR-01 | Baseboards throughout | 6" tall, paint grade, routed top edge. | |
| TR-02 | Door casings and cased openings | 4" × 1" flat stock, paint grade. Same profile at cased openings. | |
| TR-03 | Crown molding | Keep and repair, or remove; see Item 4.2. If kept, entry crown replaced to match. | TBD on cost |
| DR-01 | Interior doors | Flat panel, paint grade, with ½" applied moulding set 6" in from the door edge, mitered corners. 16 assumed; verify. | |
| DR-02 | Door hardware | Brass lever; two styles under consideration (rectangular or square rose). Owner-provided. | TBD style |
| PT-01 | Walls | Benjamin Moore White Dove OC-17, washable matte/flat; satin in bathrooms, closets and laundry. Multiple colors with contrast walls assumed; count TBD. | |
| PT-02 | Ceilings | Benjamin Moore White Dove OC-17, flat. | |
| PT-03 | Doors, trim, baseboards, casings | Sherwin-Williams Shoji White SW 7042, semi-gloss. | |
| EL-01 | Recessed lighting | LED, 2700K, 6" round, white trim, replacing the existing 6" cans in place. A few new locations possible in the front office (Phase 1) and the kitchen (Phase 2), from the unit price. | TBD added locations |
| EL-02 | Switches, dimmers, receptacles, plates | Paddle style, Lutron or equal, assumed for bidding. | TBD selection |
| EL-03 | Decorative fixtures, Phase 1 | Entry pendant, dining pendant, living room ceiling fixture (replaces the fan). Owner-provided. | TBD selection |
| FP-01 | Fireplace surround | Floor to ceiling, per the reference photo in Item 6. $8,000 allowance. Details to come. | TBD details |
| PB-01 | Free-standing tub and filler | Owner-provided, $5,000 allowance. | TBD |
Four sheets: first and second floor demo plans, each with a dimensioned version and a noted version. Click a sheet to view it at full size, or download the PDF. Notes on the sheets marked N/A are not part of this project. The wall finish level is per Item 5, not the note on the sheets.
Carry these as their own lines. Dumpsters at actual, per pull.
| Ref | Line item | Unit | Type | Notes |
|---|---|---|---|---|
| A.1 | Site protection: floors, stairs and surfaces to remain, dust partitions, HVAC register protection, both levels | LS | Base | |
| A.2 | Temporary facilities: portable toilet, temporary power and water as needed | LS | Base | |
| A.3 | Debris haul-off / dumpsters | per pull | Unit price | State container size and the number of pulls you expect. Bill at actual. |
| A.4 | Weekly clean and final clean | LS | Base | |
| A.5 | Supervision, project management, and overhead/fee | LS or % | Base | State how your fee or markup is applied (to which lines, and whether to allowances and owner-supplied items). |
Opus Signature Series engineered hardwood, 5/8" × 9½" plank, on the first floor (except the laundry and, in Phase 1, the kitchen) and on the stair treads. The existing hardwood and its plywood underlayment come out down to the slab; the slab is cleaned, patched and moisture-tested; the new floor is glued direct with a premium urethane wide-plank adhesive, which is how the flooring store recommends installing this product. The finished floor ends up lower by the plywood thickness, so the exterior door thresholds, the laundry transition and the bottom stair riser are priced separately (lines 1.6 and 9.3).
Upstairs: Karastan Tower View carpet, color Atrium, in the bedrooms, closets and hallway. Colors and products are confirmed against samples before ordering. Flooring may end up contracted directly with the flooring store; price it as its own group so it can be carved out without disturbing the rest of your bid.
| Ref | Line item | Unit | Type | Notes |
|---|---|---|---|---|
| 1.1 | Demo existing hardwood and plywood underlayment down to the slab, first floor, including haul | SF | Base | All first-floor wood rooms per Drawing 2 plus Bath One. Kitchen included (Item 7). Laundry excluded. |
| 1.2 | Demo existing carpet and pad, second floor, including haul | SF | Base | Rooms per Drawing 4. |
| 1.3 | Slab prep: scrape and clean, patch and level (cement patch), moisture test | SF | Base | State the patch product and how much you assume; note that more may be needed once exposed. |
| 1.4 | Engineered hardwood material: Opus Signature Series, 5/8" × 9½" plank | SF | Base | State waste factor, trade price and freight separately. Color to be confirmed before order. |
| 1.5 | Hardwood install, glue-down direct to slab, including premium urethane wide-plank adhesive | SF | Base | Phase 1 stops at the kitchen openings with a clean edge for later lace-in. |
| 1.6 | Height change at the lower finished floor: exterior door thresholds, transition to laundry tile, and any other transitions | EA / LS | Base | List locations. Bottom stair riser is handled in 9.3. |
| 1.7 | Carpet material: Karastan, Tower View, color Atrium | SY | Base | State waste factor and freight. Product to be confirmed before order. |
| 1.8 | Carpet pad and install, second floor bedrooms, closets and hallway | SF | Base | Specify the pad you price. Tack strip, seams, trim. |
Existing 6" recessed cans are replaced one-for-one with new 6" LED cans (2700K, white trim), in place. Count them at the walkthrough and state your count. Decorative fixtures are owner-provided and installed by you; in Phase 1 that is the entry pendant (20'-7" ceiling, lift), the dining pendant, and the living room ceiling fixture that replaces the fan. The sconces in the entry and the upstairs hall come out.
How many cans to add in the front office (Phase 1) and the kitchen (Phase 2)?
TBDNot decided. Price a new 6" can at a new location per unit (line 2.2) and we will pick the count. If a room is obviously under-lit, say so.
| Ref | Line item | Unit | Type | Notes |
|---|---|---|---|---|
| 2.1 | Replace existing 6" recessed can, one-for-one, with new 6" LED can, 2700K, white trim (retrofit into existing housing or new housing as needed) | EA | Unit price | Count existing cans at the walkthrough and state your count. State whether you would reuse the housings or replace them. |
| 2.2 | New 6" LED recessed can at a new location, 2700K, white trim, wired to existing or new switching | EA | Unit price | A few likely in the front office; the kitchen is Phase 2. |
| 2.3 | Install owner-provided decorative fixtures: dining pendant, living room ceiling fixture replacing the fan | EA | Base | Connect to existing switching. |
| 2.4 | Install owner-provided entry pendant at 20'-7" ceiling, including lift | EA | Base | |
| 2.5 | Remove sconces, abandon j-box, patch: Entry (2), Second Floor Hallway (2) | EA | Base | |
| 2.6 | Electrical general: new homeruns, circuits and panel work required by lighting and device changes | LS | Base | Keep separate from the per-light prices. |
New switches, dimmers, receptacles and plates in all Phase 1 rooms. Dimmers that control nothing come out, box removed and wall patched; confirm with us before removing anything that turns out to control a load.
Which switches and plates?
TBDNot selected. For bidding assume paddle-style devices and plates, Lutron or equal. Split material and labor so the selection can change without re-bidding.
| Ref | Line item | Unit | Type | Notes |
|---|---|---|---|---|
| 3.1 | New switches, dimmers, receptacles and plates throughout the Phase 1 rooms | EA | Unit price | Assume paddle-style devices and plates, Lutron or equal. Split material and labor so the selection can change. State your device count. |
| 3.2 | Remove dead or unconnected dimmers/switches, remove box, patch | EA | Base | Confirm with us before removing anything that controls a load. |
All baseboards, door casings, trim and interior doors come out and are replaced: 6" paint-grade baseboard with a routed top edge; 4" × 1" flat-stock casing at every door and every cased opening; flat-panel paint-grade doors with ½" applied moulding set 6" in from the edge, mitered corners, about 16 (verify); owner-provided hardware installed. The existing decorative transom stays as it is.
Window casings: remove them now, while the drywall is being refinished, or wait until the windows are replaced?
AlternateContractorTBDWindows are not part of this project, so this is a timing question. Price line 4.7 as an alternate: remove the casings, stools and aprons and finish the openings with drywall returns and a painted sill at every window in the rooms getting wall work. Tell us how much of that gets torn up again when the windows are replaced later.
Keep or remove the crown molding?
AlternateTBDPrice both: A, keep, repair, caulk and paint it everywhere it exists (line 4.8); B, remove it all, patch and finish (line 4.9). If it is kept, the entry crown is replaced with a matching profile at the 20'-7" ceiling (line 4.10). For each drywall option in Item 5, say whether the crown has to come down.
Front office crown: replace it, or paint the dark wood in place?
AlternateTBDPrice both (lines 4.11 and 4.12). We will pick on cost and on your view of how well stained wood takes paint.
| Ref | Line item | Unit | Type | Notes |
|---|---|---|---|---|
| 4.1 | Demo all baseboards, door casings, trim and interior doors, both levels (kitchen trim goes with the kitchen demo) | LS | Base | |
| 4.2 | Baseboard: 6" paint grade with routed top edge, both levels | LF | Base | State your LF count. Not in the kitchen in Phase 1. |
| 4.3 | Interior doors: flat panel paint grade slab, jamb, ½" applied moulding 6" inset with mitered corners, hang and adjust | EA | Base | 16 assumed; field verify. |
| 4.4 | Door casing: 4" × 1" flat stock, paint grade, both sides | per door | Base | |
| 4.5 | Door hardware install (owner-provided) | EA | Base | Bore, set, adjust. |
| 4.6 | Casing at cased openings, new profile to match door casings | EA opening | Base | List openings. |
| 4.7 | ALTERNATE: remove window casings, stools and aprons; drywall returns and painted sill at all windows in rooms getting wall work | EA window | Alternate | See Item 4.1. State how much of this would be redone when windows are replaced later. |
| 4.8 | ALTERNATE A: keep existing crown: protect, repair, caulk and paint | LS | Alternate | State whether your drywall approach (Item 5) requires removing it. |
| 4.9 | ALTERNATE B: remove all crown, patch and finish walls and ceilings | LS | Alternate | |
| 4.10 | Entry crown: replace with a profile matching the rest of the house, including lift (if crown is kept) | LF | Base | |
| 4.11 | Front office crown: replace to match the rest of the house | LF | Alternate | Price 4.11 and 4.12 both; we pick on cost. |
| 4.12 | Front office crown: prime and paint the existing dark wood crown in place | LS | Alternate | |
| 4.13 | Paint all trim, doors, casings and base: SW Shoji White 7042, semi-gloss, zero/low VOC | LS | Base |
Two groups. Group A is the first-floor common rooms (entry, front office, living room, breakfast room, dining room, hallway), the stairwell, and the second-floor hallway. Group B is the bedrooms and their closets, priced separately so we can include them or not. Bathrooms get no drywall work. The pantry and laundry get paint only. The kitchen is Phase 2.
The texture is not uniform, there are bad patches, some proud of the wall, and in the living room and entry the studs bow into the room and the seams show. A Level 3 refinish, or retexturing and paint, may not fix that.
ContractorWalk the living room and entry with us and tell us what you would do about the bowed studs and visible seams. A skim coat or new texture does not straighten a wall; we want to know whether you would re-hang those areas, shim or plane the studs, overlay, or something else.
Which finish method? We want to pick on cost and outcome.
AlternateTBDPrice each option as its own line at a per-SF rate, Group A and Group B extended separately, and say which of the problems above it fixes and which it does not. State the wall and ceiling SF each rate covers, by group, including the 20'-7" entry.
| Ref | Line item | Unit | Type | Notes |
|---|---|---|---|---|
| 5.1 | OPTION 1: texture repair. Feather and blend bad patches and uneven texture, re-texture to match, prime | SF | Alternate | Group A and Group B extended separately. State which of the listed problems this does and does not fix. |
| 5.2 | OPTION 2: Level 3. Remove or skim texture, tape and float, uniform new light texture | SF | Alternate | A and B separately. Name the texture you would apply (light orange peel, light knockdown, etc.). |
| 5.3 | OPTION 3: Level 4. Remove texture, tape and float with a full third coat over joints and fasteners, no texture, ready for flat paint | SF | Alternate | A and B separately. |
| 5.4 | OPTION 4: Level 5 smooth. Level 4 plus full skim coat, walls and ceilings | SF | Alternate | A and B separately. |
| 5.5 | OPTION 5: overlay. New ¼" or ⅜" drywall over existing walls (ceilings where needed), taped and finished; include device box extenders, jamb extensions and trim impacts | SF | Alternate | A and B separately. Say where you would and would not overlay. |
| 5.6 | OPTION 6: targeted repair. Cut out and re-hang drywall at bowed studs and visible seams (living room, entry), shim or straighten studs, finish to match the whole-house option | LS or SF | Alternate | Walk the living room and entry and tell us what you would do. |
| 5.7 | Patch, float and finish at all demo locations (millwork, built-in chests, sconces, removed devices, security panel, vanity light relocation) | LS | Base | Or state that it is included in your wall option. |
| 5.8 | Paint walls, Group A and Group B: BM White Dove OC-17, washable matte; satin in closets; zero VOC | SF | Base | A and B extended separately. State the product line. Primer included. |
| 5.9 | Paint ceilings, Group A and Group B: BM White Dove OC-17, flat; zero VOC | SF | Base | Include the 20'-7" entry. |
| 5.10 | Pantry and laundry: paint walls and ceilings only, no drywall refinish (satin in laundry) | LS | Base | |
| 5.11 | Bathrooms: paint walls and ceilings only, satin, no drywall refinish | per bathroom | Unit price | Bath One, Bath Two, Primary Bath (17'-8" vault). We may drop any of these. |
| 5.12 | Contrast/accent walls in a second color | EA wall | Unit price | Count TBD. |
Demo the existing hearth, mantel and brick surround (line 6.1). New floor-to-ceiling surround per the reference photo below: $8,000 allowance (line 6.2). More detail to come. The ceiling fixture that replaces the fan is owner-provided; install is in line 2.3.

| Ref | Line item | Unit | Type | Notes |
|---|---|---|---|---|
| 6.1 | Demo hearth, mantel and brick surround | LS | Base | |
| 6.2 | New floor-to-ceiling surround per the reference photo | Allowance | Allowance | $8,000 allowance. Details to come. |
Phase 1 is a full demo, then cap and make safe, then leave it: remove cabinetry, countertops, backsplash, the island, plumbing fixtures, decorative lighting and trim; disconnect and remove the appliances (we will say which are kept); cap the plumbing and gas, cap the island vent, and make the electrical safe. Kitchen floor, walls and ceiling are not finished in Phase 1; the new flooring stops at the kitchen openings. Phase 2The build-out is a separate quote on its own schedule; the appendix summarizes it so you know what is coming. Do not include it in the Phase 1 number.
The kitchen–dining opening is shorter than the dining–entry opening. Raise it to match?
AlternateContractorTBDPrice it as a Phase 1 alternate (line 7.3), since the dining-room side is getting wall work now: raise the head of the opening to match the dining–entry opening, including header, dining-side drywall, casing and finish. Tell us whether that wall is load-bearing and what you would do about it if so.
| Ref | Line item | Unit | Type | Notes |
|---|---|---|---|---|
| 7.1 | Full kitchen demo: cabinetry, countertops, backsplash, island, plumbing fixtures, decorative lighting, trim; disconnect and remove appliances; haul | LS | Base | We will say which appliances are kept and set aside. |
| 7.2 | Cap and make safe: plumbing, gas, island vent; electrical made safe | LS | Base | |
| 7.3 | ALTERNATE: raise the head of the kitchen–dining opening to match the dining–entry opening height: header, dining-side drywall, casing, finish | LS | Alternate | State whether the wall is load-bearing and what you would do about it. |
Bath One gets the new hardwood now, same glue-down method: existing floor out to the slab, toilet pulled and reset, transition at the door (line 8.1). The vanity light box moves to center on the vanity (line 8.2). No other wall work in this room; paint is line 5.11.
| Ref | Line item | Unit | Type | Notes |
|---|---|---|---|---|
| 8.1 | Bath One flooring: existing floor out to the slab, toilet pulled and reset, slab prep, glue-down hardwood, transition at door | LS | Base | |
| 8.2 | Relocate the vanity light j-box to center on the vanity; patch | EA | Base |
New Opus treads with matching stairnose (16, verify) over painted risers, Benjamin Moore White Dove OC-17 (17, verify). New handrail and newel posts in solid wood of the flooring species, stained to match the floor; black metal balusters. Because the first floor drops by the plywood thickness (Item 1), the bottom riser gets taller: include the fix in line 9.3 and tell us how you would keep the risers even. In the entry, the abandoned security panel and keypads, the doorbell chime, and any other dead wall devices found at the walkthrough come out, wiring abandoned safely and walls patched (line 9.6); whether a replacement chime is wanted is undecided.
Stair design: tread construction, how far the treads extend, post design, baluster profile, who fabricates the rail?
TBDContractorAll open. Propose the tread construction you would use (solid tread or plank-wrapped with stairnose) and price both if they differ; tell us what nosing overhang you recommend. Name the fabricator you would use for the rail and posts, or tell us if we should buy them direct, and provide stain samples on the actual species. Opus stairnose pieces exist and have been priced for this staircase before; confirm availability and lead time. An engineered plank cannot be milled into a rail or post, which is why the rail and newels are solid wood matched to the floor.
| Ref | Line item | Unit | Type | Notes |
|---|---|---|---|---|
| 9.1 | Demo stair treads, railing, balusters and newel posts; temporary safety rail during construction | LS | Base | |
| 9.2 | Stair tread material: Opus tread or plank with matching stairnose | EA | Base | 16 treads assumed; field verify. State the tread construction you propose. |
| 9.3 | Stair tread fabrication and install, including skirt and nosing detail and the bottom-riser adjustment for the lower first floor | EA | Base | Tell us how you would keep the risers even. |
| 9.4 | Risers: prep and paint BM White Dove OC-17 | EA | Base | 17 assumed; field verify. |
| 9.5 | Handrail and newel posts: solid wood of the flooring species, stained and finished to match the floor; black metal balusters | LF rail + EA newel | Base | Name the fabricator. Provide stain samples. Post design TBD. |
| 9.6 | Remove abandoned security panel(s) and keypad, doorbell chime, and other abandoned wall devices; abandon wiring safely; patch | LS | Base | Replacement chime TBD; price as an optional add if you like. |
All built-in cabinetry, including the gun case, comes out and is hauled; the wall and floor are repaired at the demo (lines 10.1 and 10.2). Crown: see Item 4.3.
What happens to the french doors?
AlternateTBDNot decided. Price three alternates: A, keep them, prep and paint (line 10.3); B, replace them with new doors to the door spec and install owner-provided hardware (line 10.4); C, remove the doors and jamb and case the opening (line 10.5).
| Ref | Line item | Unit | Type | Notes |
|---|---|---|---|---|
| 10.1 | Demo all built-in cabinetry including the gun case; haul | LS | Base | |
| 10.2 | Wall and floor repair at millwork demo | LS | Base | |
| 10.3 | French doors ALTERNATE A: keep, prep and paint | LS | Alternate | |
| 10.4 | French doors ALTERNATE B: replace with new doors to the door spec (flat panel, applied moulding), hang, install owner-provided hardware | LS | Alternate | |
| 10.5 | French doors ALTERNATE C: remove doors and jamb, case the opening | LS | Alternate |
The built-in chests in both primary closets come out and are hauled; walls and floor are patched and finished; nothing goes back in their place. The closets then get carpet, base and paint with the rest of the second floor.
| Ref | Line item | Unit | Type | Notes |
|---|---|---|---|---|
| 11.1 | Demo built-in chests in both primary closets; haul | LS | Base | Nothing goes back in their place. |
| 11.2 | Patch and finish walls and floor at demo | LS | Base |
Install a new free-standing tub and tub filler (owner-provided, $5,000 allowance) with the associated plumbing. Existing flooring and walls otherwise stay; patch and paint only where the tub work disturbs them.
| Ref | Line item | Unit | Type | Notes |
|---|---|---|---|---|
| 12.1 | Demo existing tub and surround as required; protect existing flooring | LS | Base | |
| 12.2 | Free-standing tub and filler rough-in, set and finish (owner-provided tub and filler, $5,000 allowance) | LS | Base | Relocate supply and waste as required. |
| 12.3 | Patch and paint at tub wall; floor patch at old drain location | LS | Base |
Everything still open, who owns it, and how it is handled in the bid so pricing can proceed now.
| Ref | Decision | Owner | Needed to decide | Bid treatment |
|---|---|---|---|---|
| 1 | Opus color; confirm carpet product | Owners | Samples | Price as listed; color does not change price |
| 2.1 | Added can lights in the front office (Phase 1) and kitchen (Phase 2) | Owners | Unit price; existing count | Unit price per new location; replacements one-for-one |
| EL-03 | Decorative fixture selections | Owners | Selections | Owner-provided; install labor priced |
| 3.1 | Switch, dimmer and plate selection | Owners | Selection | Assume paddle-style, Lutron or equal; material and labor split |
| 4.1 | Window casings now or with the windows later | Owners | Alternate price; contractor's view on rework | Alternate 4.7 |
| 4.2 | Keep or remove crown | Owners | Alternates A and B; drywall option chosen | Alternates 4.8 / 4.9; 4.10 if kept |
| 4.3 | Front office crown: replace or paint | Owners | Two alternate prices | Alternates 4.11 / 4.12 |
| 5.2 | Wall and ceiling method; whether bedrooms (Group B) are included | Owners with contractor advice | Six option prices by group; walkthrough of living room and entry | Options 5.1–5.6 as unit rates, A and B extended separately |
| 6 | Fireplace details beyond the reference photo | Owners | More to come | Demo line 6.1; $8,000 allowance line 6.2 |
| 7.1 | Raise kitchen–dining opening | Owners | Alternate price; structural answer | Alternate 7.3 |
| 9.1 | Stair design: tread construction, nosing, newel posts, baluster profile, fabricator | Owners with contractor | Proposal and samples | Price both tread constructions |
| 9 | Replacement doorbell chime | Owners | Preference | Optional add |
| 10.1 | French doors: keep, replace or remove | Owners | Three alternate prices | Alternates 10.3–10.5 |
| DR-02 | Door hardware style | Owners | Preference | Owner-provided; install priced per door |
| PT-01 | Accent wall count and colors | Owners | Paint plan | Unit price per wall |
Not part of the Phase 1 price. Listed so you know what follows and can quote it separately when the design is final. Working assumptions: new layout with a larger island; stain-grade flat-panel cabinetry, about 41 LF on the range and sink walls including uppers, 7 LF of floor-to-ceiling cabinetry at the fridge wall with an appliance garage, and 6 LF of island millwork; Level 5 quartzite countertops with a mitered edge; tile backsplash at a $20/SF allowance; under-cabinet LED tape; a decorative vent hood ducted to the exterior; the range moves off the island. Owner-provided: appliances ($36,000 allowance), plumbing fixtures ($6,000 allowance), cabinet hardware, and three pendants.
| Ref | Line item | Unit | Type | Notes |
|---|---|---|---|---|
| K.1 | Layout modification and new framing per final plan | LS | Base | |
| K.2 | New threshold, framing and concealed door to hallway | LS | Base | |
| K.3 | Cabinetry: range wall and sink wall including uppers, stain-grade flat panel doors and drawers (~41 LF) | LF | Base | State whether finishing is included; if not, see K.6. |
| K.4 | Cabinetry: fridge wall, floor to ceiling, with appliance garage (~7 LF), stain grade | LF | Base | |
| K.5 | Island millwork (~6 LF, larger island), stain grade | LF | Base | |
| K.6 | Cabinet finishing (if not in K.3–K.5) | LF | Base | |
| K.7 | Decorative vent hood fabrication | Allowance | Allowance | Design, material and finish TBD. |
| K.8 | Countertop material: Level 5 quartzite | per slab | Allowance | State the slab count you assume. |
| K.9 | Countertop fabrication and install: template, mitered edge, cutouts, seams, set | SF | Base | ~130 SF; verify against final elevations. |
| K.10 | Backsplash tile material | SF | Allowance | $20/SF allowance. |
| K.11 | Backsplash install: prep, set, grout, seal | SF | Base | |
| K.12 | Under-cabinet LED tape 2700K with concealed routed detail or trim, driver and dimming | LF | Base | ~32 LF assumed. |
| K.13 | Kitchen electrical rough and finish: appliance circuits, island, disposal, hood, devices, 6" can lights | LS | Base | |
| K.14 | Kitchen plumbing rough and finish for the new layout; set owner-provided fixtures and disposal | LS | Base | Fixtures owner-provided ($6,000 allowance): sink, faucet, hot/cold/sparkling faucet, disposal. |
| K.15 | Gas line relocation to the new range wall, if required | LS | Contingent | |
| K.16 | Range hood duct to exterior; chase framing and patch | LS | Base | State the route you assume. |
| K.17 | Makeup air system if the hood exceeds 400 CFM | LS | Contingent | |
| K.18 | Kitchen flooring: slab prep and glue-down hardwood laced into the Phase 1 floor | SF | Base | |
| K.19 | Kitchen walls and ceiling: finish to match the whole-house option; paint | SF | Base | |
| K.20 | Appliance delivery, set and install (owner-provided package, $36,000 allowance) | LS | Base | |
| K.21 | Cabinet hardware install (owner-provided, ~62 pieces) | EA | Base | |
| K.22 | Install owner-provided pendants: sink (1), island (2) | EA | Base |